College Park Community Center Playground Replacement
College Park Community Center Playground Replacement
Project Background/Description
The Department of Parks and Recreation, in partnership with the Prince George’s County Board of Education (B.O.E.), is replacing the playground equipment at the College Park Community Center. The playground is located on (B.O.E.) property behind the Paint Branch Elementary School adjacent to the College Park Community Center.
The playground replacement will update and improve the existing playground facilities and feature Autism Sensory/Inclusive Play items and outdoor educational learning. The new playground will have a cumulative square footage of less than 9,824.
Improvements involve the removal and disposal of the existing equipment and the installation of new play equipment, engineered-wood-fiber safety surfacing, and ADA accessibility upgrades.
The updated playground will have equipment for children ages 2-5 and 5-12. Play elements and features will allow for climbing, spinning, swinging, sliding, and more! ADA improvements include new accessible parking and site access to the playground.
Status/Project Updates
Currently, the project is in the Preparation and Research phase. A summary of anticipated milestones is as follows:
Winter 2021 – Community Engagement
Spring 2022 –Design
Summer 2022 –Construction Documents / Permits
Fall 2022 –Construction Bid
Winter 2022 –Construction Start
Late Spring 2023 –Construction Completion
The anticipated project completion is Spring 2023.
Actual dates for the completion of the milestones are subject to change.