Project Schedule

  1. August through September 2013
    • Project Initiation and Review
    • Project Website Launch
    • Stakeholder Interviews
  2. September through December 2013
    • Market and Physical Assessment
    • Community Meeting 1, October 2013
  3. November 2013 through April 2014
    • Case Study Review
    • Study Development and Implement Strategies
    • Community Meeting 2, March 2014
  1. April through October 2014
    • Draft Study
    • Draft Poster
    • Finalize Comments on Draft
  2. March through September 2015
    • Finalize Study
    • Finalize Poster
    • Request to Release Study to the Public and Poster
    • Planning Board Meeting, September 2015
Graphic Detailing the Kenilworth Timeline